Project Update: Casey Green - N4S8

Casey Green August 2023

Part 3 is progressing and heading towards completion in 2023.

Part 4 is almost half completed.

Project Update: Casey Green - N4S8

Casey Green February 2023

Stage 8 Part 1 is nearing completion!

Part 1 with lots 160-166 has completed plastering and joinery installation with Part 2 (lots 222-230) approaching its completion of the framing process, with internal works well underway.

Part 3 has also well and truly taken shape with framing progressing rapidly.

N4 Park Update

Casey Green Park Update 2023

Find out why the opening of the Neighbourhood 4 park has experienced delays.

Read the full update in the link.

Project Update: Casey Green - N2S4

Casey Green January 2023

We have just commenced construction recently for Neighbourhood 2, with 90% of ground floor framing completed (lots 246-252).