Project Update: Casey Green - N4S8
Casey Green August 2023
Part 3 is progressing and heading towards completion in 2023.
Part 4 is almost half completed.
Casey Green August 2023
Part 3 is progressing and heading towards completion in 2023.
Part 4 is almost half completed.
Stage 8 Part 1 is nearing completion!
Part 1 with lots 160-166 has completed plastering and joinery installation with Part 2 (lots 222-230) approaching its completion of the framing process, with internal works well underway.
Part 3 has also well and truly taken shape with framing progressing rapidly.
Find out why the opening of the Neighbourhood 4 park has experienced delays.
Read the full update in the link.
We have just commenced construction recently for Neighbourhood 2, with 90% of ground floor framing completed (lots 246-252).